Owner: ROICC Department of the
Navy.
Date of Award: 9/94
Contract Value Awarded: $3,500,000
Project % performed by WCC: 55%
Major Subcontractors:
Dynamic Drywall, Blue Mt. Steel, Miracle Electric
Project Description: This project
included the renovation of four 3-story BEQs. Interior walls were
demolished and replaced. New electrical and mechanical
systems were installed, new room layout, and new exterior insulated finish
system (EIFS).
Problems / Solutions: After approx.
20% of the project was complete, it was discovered that the entire plumbing
system in the building was corroding and would have to
be replaced. This added approximately 6000 man-hours of labor. Concurrently,
the owner requested that the project schedule be
shortened by one week to accommodate an incoming CAG (Carrier Air Group). WCC
immediately deployed a secondary crew and began
working double shifts. Due to our immediate response and close coordination,
the project was completed on time and on budget.
|