Value Awarded: $3,544,700 Project
% performed by WCC: 38% Major Subcontractors: Dynamic Drywall, Hometown Construction
Project Description: Project scope
included complete renovation of four 3-story BEQs. Work included selective demolition, installation of new finishes,
renovation of bathrooms and room layouts, upgrading of all electrical and security systems, installation of new casework, and
construction of a new kitchen facility.
Problems / Solutions: Shortly after
award, the owner requested that the start of the project be delayed several months. WCC used this time to develop a new work plan
and project schedule in order to finish the project on time. WCC had materials for the project shipped to a storage facility near
the site. Once notice to proceed was issued, WCC worked double shifts and was able to complete a project initially scheduled for 18
months in only 7 months. |
|